PROJECT REFERENCES
A reference is a verifiable record, not a logo wall
Each project below is given with its unit, client, dates and man-hour load. These figures are the concrete measure of the scope we have carried in refining, petrochemical, power, mining and critical infrastructure.
2,044,000Man-hours on a single project
(STAR Refinery)
5,600,000+Man-hours in refining and
petrochemical work alone
4,500+ MWCombined-cycle and thermal
power plant insulation scope
18+ yearsUnbroken framework collaboration
with a single client
STAR Refinery — SOCAR
Aliağa, İzmir · 2017–2018
Consortium: Técnicas Reunidas · Saipem · GS · Itochu
Thermal and cold insulation of process units, pipelines and equipment; cladding, vapour barrier details and site quality control.
2,044,000Man-hours1,033Peak headcount
Delivered ahead of programme with zero accidents. Named best subcontractor on site by TSGI.
Tüpraş Kocaeli Refinery and RUP
Kocaeli · 2003–2005 and 2013–2014
Main contractor: TEKFEN A.Ş.
Insulation works across the İzmit refinery and insulation of new units under the Residuum Upgrading Project.
2,727,000Man-hours (two projects)570Peak headcount
Both projects completed ahead of programme with zero accidents.
PETKİM Petrochemicals — Planned Shutdown
Aliağa · 2022
Client: SOCAR
All insulation works across the plant within the shutdown window; removal, inspection, replacement and recommissioning.
840,000Man-hours420Peak headcount
Delivered ahead of a time-critical shutdown programme with zero accidents.
Cengiz Holding 600 MW CCPP
Tekkeköy, Samsun · 2017–2018
Turnkey scope for all insulation works
Complete thermal and acoustic insulation of the gas turbine, HRSG, steam lines and balance-of-plant equipment.
23 monthsTotal duration2 monthsAhead of programme
The plant was commissioned with a completion-time record in its class.
RWE 775 MW and OMV 890 MW CCPP
Denizli 2019 · Samsun 2013
Main contractor: METKA
Insulation of turbines, HRSG, steam and BOP lines at combined-cycle power plants; acceptance against international EPC specifications.
1,665 MWCombined installed capacity2International EPC projects
Delivered against the acceptance criteria and quality-dossier requirements of European energy operators.
Eti Bakır — Samsun and Mazıdağı
Tekkeköy, Samsun: since 2007
Mazıdağı: since 2017
Continuous site service across long-term maintenance, planned shutdowns and capital projects; insulation renewal and capacity-increase works.
18+ yearsUnbroken collaboration2Separate operating sites
The clearest evidence of continuity under long-term framework agreements.
Camsan MDF III — turnkey (EPC) plant installation2019–2021Camsan A.Ş. · Dieffenbacher615,592 man-hours
Cenal Karabiga Integrated Thermal Power Plant2017–2018Cengiz Holding · Alarko Holding2×660 MW
Yunus Emre Thermal Power Plant + turnkey HVAC2013–2014Vitkovice Power AS2×145 MW · 9,000 m² ducting
Eti Alüminyum Seydişehir Facilities2009–2011Eti Alüminyum A.Ş.3 turnkey projects
Çayırhan Thermal Power Plant2000–2002Güriş Holding4×150 MW
Orhaneli Thermal Power Plant1999–2001NOEL · KRC · Siemens210 MW
İGA Istanbul Airport — ATC Control Tower2018–2020Main contractor: MNGAll mechanical works
Kuwait International Airport — Modernisation2018–2020Main contractor: Cengiz HoldingInternational project
Söke Cement Plant1995–1996ENKA İnşaat ve Sanayi A.Ş.Insulation · piping · scaffolding
Alkim Alkali Kimya — Sodium Sulphate Plants2010–2011Alkim Alkali Kimya A.Ş.Process insulation
These projects were carried out under the responsibility of our founder and his team, either under a direct client contract or under a main contractor. Scope, the role undertaken and dates are documented separately for each project; reference letters and completion certificates are shared on request. Work under defence, aerospace and space programmes is not listed here, as required by confidentiality agreements.