Insulation ITP inspection and test plan

An ITP is a table with five honest columns: what activity, against what reference, inspected by whom, to what acceptance criterion, producing what record. Insulation ITPs go wrong in the fourth and fifth columns — criteria written as a standard number, and records nobody names until handover, when they do not exist.

Activity breakdownH, W, S and R point typesMeasurable acceptance criteriaRecord and dossier structure
Insulation inspection and test plan with hold and witness points
1,000,000+ m²Completed insulation application
15,000+ MWPower plant capacity insulated
20+ yearsEngineering and site experience
3 continentsProject delivery
Scope

Five columns and where each one fails

The structure is standard. What separates a working ITP from a filed one is how specifically each column is filled in.

01

Activity and reference

Work broken down to the level at which it is actually inspected, each line tied to the specification clause or drawing that governs it.

02

Intervention and responsibility

Hold, witness, surveillance or review, and who performs each. A hold point with no named attendee becomes a surveillance point the first time the schedule is tight.

03

Criterion and record

What constitutes acceptance, expressed as something measurable, and the specific record that proves it — named at the planning stage, not reconstructed at handover.

Hold points cost schedule time

Every hold point stops work until an inspector attends. Too many and the programme suffers; too few and there is no evidence. We set the number against the actual risk of each activity and say why.

Insulation ITP structure with acceptance criteria and records
Method

How the plan is built

We work from the specification clause by clause, identify what each clause requires someone to verify, and place an intervention only where verification is not possible after the fact. Insulation is a covering trade, so most of its criteria become unverifiable the moment the cladding goes on.

  • Specification read clause by clause, each verifiable requirement captured
  • Intervention placed where later verification becomes impossible
  • Acceptance criteria written as measurements, tolerances or stated conditions
  • Record format named for every line, with the responsible party
  • Third party and client witness points agreed before issue, not after
Deliverables

What you receive ready for project approval

The plan and its forms are issued together, because an ITP whose record forms do not exist yet will not produce records.

Inspection and test plan

Full table by activity, with reference, intervention, criterion and record.

Record forms

The actual check sheets each line calls for, formatted for site use.

Criteria annex

Where an acceptance criterion needs a tolerance table or a sketch to be usable.

Responsibility matrix

Who performs, who witnesses and who approves, for each intervention.

Dossier index

How the records assemble into the final quality dossier at handover.

Review note

Specification clauses that cannot be verified as written, and what we suggest instead.

Inspection of insulation layers before cladding conceals the work
Covering trade

Insulation covers the evidence of its own quality

Surface condition, vapour barrier continuity, joint sealing and layer thickness are all invisible once cladding is fitted. There is no non-destructive way to confirm them later. That single fact is what should drive where the hold points go, and it is the argument we make when a client wants fewer of them.

  • Substrate condition recorded before the first layer is applied
  • Vapour barrier continuity inspected before it is covered
  • Layer thickness and joint staggering checked in place, with photographs
  • Cladding fixing and weatherproofing inspected as a separate activity
  • Photographic record tied to line number and date, not stored loose

Industrial Insulation Catalogue

Engineering scope, calculation and documentation services, material families and application capability in a single document.

Open the 2026 catalogue

Working worldwide

ERATHERM works as an engineering partner for operators, EPC contractors and equipment manufacturers. Calculation, design, documentation and specification work is delivered remotely under the client's document control procedure; inspection, site supervision and application teams are mobilised to site.

  • Europe, the Middle East, Asia, Africa and the Americas
  • EPC-level deliverable documentation
  • Client document control procedure
  • Remote engineering and site mobilisation
Questions

Inspection and test plans questions we are asked

How many hold points should an insulation ITP have?

Few enough that the programme survives and enough that covered work is witnessed. In practice the substrate condition and the vapour barrier on cold service are the two that justify a genuine hold; most of the rest can be surveillance with a record.

Who issues the ITP, the contractor or the owner?

The contractor normally issues it and the owner approves it. Where an owner wants control of the criteria, we write it on the owner's behalf and the contractor adopts it — which also removes the review cycle that usually follows a contractor-written plan.

What makes an acceptance criterion unusable?

A bare reference. Citing a standard does not tell an inspector standing at the work front what to accept. The criterion has to be the number, the tolerance or the condition itself, with the standard cited beside it.

Can you run the inspections as well as write the plan?

Yes. Third party inspection against the ITP is a separate service and is often the better arrangement on projects where the installing contractor would otherwise be inspecting its own covered work.

Send the specification and the scope

We will produce an ITP with criteria an inspector can actually apply and record forms that exist before the work does.