A reference is not a logo wall. It is a record that can be verified by unit, by man-hours and by delivery performance. Below is a selection of recent projects in refining, power, mining, cement and critical infrastructure, presented with their scope. Defence, aviation and space projects are not shown here because of the confidentiality agreements that cover them.

ERATHERM fields of work for industrial plants and for defence, aviation and space platforms
1,000,000+m² of Completed Insulation Application
15,000+MW of Installed Power Plant Insulation
8,000,000+Man-Hours of Completed Work
3Continents: Europe, Asia and Africa
Recent Selection

This Page Is a Selection, Not the Full Reference List

More than twenty years of projects do not fit on one page. What follows is a sector-by-sector selection of recent work, presented at unit level with documented site data. The full reference file is shared on request.

Client logos from the ERATHERM industrial project portfolio

About Our Defence, Aviation and Space References

The projects we carry out in the defence, aviation and space sectors are covered by non-disclosure agreements , so their scope and content cannot be published here. For our capabilities and the work we do in this field, see our Defence, Aviation and Space industry page.

Capability Catalogues

Project records and technical scope of work

Our industrial site experience and our engineering scope in defence, aviation and space programmes are set out in two separate catalogues.

INDUSTRIAL PLANTS

Industrial Insulation Catalogue 2026

Thermal and cryogenic insulation for refining, power and process plants: system design, material supply, site application and quality control.

Open / Download the Catalogue

DEFENCE · AVIATION · SPACE

Defence and Space Capability Catalogue 2026

Thermal control, vacuum and MLI, cryogenic, acoustic and test support. Confidential project and platform data are not published; technical scope is discussed under an NDA.

Open / Download the Catalogue
Refining & Petrochemicals

Selected Recent References in Refining and Petrochemicals

STAR Refinery SOCAR, piping and equipment insulation application

STAR Refinery — SOCAR

Aliağa · İzmir, Türkiye2017–2018Consortium: Tecnicas Reunidas · Saipem · GS · Itochu

Scope — Piping and Equipment Insulation Application

  • Unit 110 — VDU (Vacuum Distillation Unit)
  • Unit 140 — DHT (Diesel Hydrotreating Unit)
  • Unit 150 — KHT (Kerosene / Jet Fuel Hydrotreating Unit)
  • Unit 630 — Plant and Instrument Air Unit
  • Unit 640 — Nitrogen Production Unit
1,033 Peak Workforce2,044,000 Man-Hours

Delivered ahead of programme with a zero accident record; named best subcontractor on site by TSGI.

Tüpraş RUP Residuum Upgrading Project insulation application

Tüpraş RUP (Residuum Upgrading Project)

Kocaeli2013–2014Main Contractor: TEKFEN A.Ş.

Scope — Piping and Equipment Insulation Application

  • Delayed Coker Unit
  • Hydrocracker / Unicracking Unit
  • Vacuum Distillation Unit
  • Hydrogen Production Unit
420 Peak Workforce1,086,000 Man-Hours

Delivered ahead of programme with a zero accident record.

Tüpraş Kocaeli Refinery insulation application

Tüpraş Kocaeli (İzmit) Refinery

Kocaeli2003–2005Main Contractor: TEKFEN

Scope — Piping and Equipment Insulation Application

  • Crude Distillation Units (CDU — PLT 25/36 and others)
  • Reforming Unit (Platformer — PLT 7 and others)
  • Tank Farms
570 Peak Workforce1,641,000 Man-Hours

Delivered ahead of programme with a zero accident record.

PETKİM Aliağa planned shutdown, complete insulation scope

PETKİM Petrochemicals — Complete Shutdown Insulation Scope

Aliağa, Türkiye2022Client: SOCAR

Scope — Planned Shutdown, Piping and Equipment Insulation

  • Ethylene · Aromatics · LDPE · HDPE · PP Plants
  • PVC · ACN · PTA · MEG Plants
420 Peak Workforce840,000 Man-Hours

The entire shutdown insulation scope was delivered ahead of programme with a zero accident record.

Enerji Santralleri

Selected Recent References in Power Generation

RWE Denizli 775 MW combined cycle plant insulation

RWE 775 MW CCPP — Combined Cycle Power Plant

Denizli2019Main Contractor: METKA (Greece)

Scope — Piping and Equipment Insulation Application

  • Gas Turbine · Steam Turbine · HRSG Sections
  • Air Cooled Condenser (ACC) Section
  • RMS-A Gas Station · Demineralised Water Unit
Cengiz Holding 600 MW CCPP turnkey insulation

Cengiz Holding 600 MW CCPP — Turnkey Complete Insulation

Tekkeköy · Samsun, Türkiye2017–2018Client: Cengiz Holding

Scope — Complete Insulation Application

  • Gas Turbine · Steam Turbine · HRSG
  • Sea Water Cooling System · RMS-A Gas Station
  • Central Control Room (CCR) — Insulation and HVAC

The plant was completed in 23 months, two months ahead of schedule and a world record completion time in its class. The entire insulation scope was delivered turnkey by ERATHERM.

OMV Samsun 890 MW natural gas combined cycle plant insulation

OMV 890 MW CCPP — Samsun Natural Gas Combined Cycle Plant

Samsun2013Main Contractor: METKA

Scope — Piping and Equipment Insulation Application

  • Gas Turbine · Steam Turbine · HRSG
  • Sea Water Intake and Cooling Station
  • Water Treatment and Demineralisation Unit
Cengiz Holding 240 MW CCPP turnkey insulation

Cengiz Holding 240 MW CCPP — Turnkey Insulation

Tekkeköy · Samsun, Türkiye2009–2010Client: Cengiz Holding

Scope — Insulation Application

  • General Electric (GE) Gas Turbines · Steam Turbine
  • Heat Recovery Steam Generators (HRSG)
  • Demineralisation Unit · CCR (Insulation and HVAC)

The entire insulation scope of the plant was completed by ERATHERM.

Yunus Emre 2x145 MW thermal power plant insulation and HVAC

Yunus Emre CFPP — 2×145 MW Coal Fired Power Plant

Eskişehir, Türkiye2013–2014Main Contractor: Vitkovice Power AS

Scope — Insulation Application and HVAC

  • Circulating Fluidised Bed Boilers (CFB) and Boiler House
  • Andritz Turbo-CDS FGD (Dry Flue Gas Desulphurisation) · ESP Area
  • Turbine and Generator Hall

In addition to the insulation scope, the complete turnkey HVAC works were delivered by ERATHERM, including some 54 AHU units and 9,000 m² of HVAC ducting.

Cenal Karabiga 2x660 MW integrated thermal power plant insulation

Cenal Karabiga Integrated Thermal Power Plant — 2×660 MW

Karabiga2017–2018Client: Cengiz Holding · Alarko Holding

Scope

  • Turbine and Boiler Insulation Application
  • Insulation Consultancy
Çayırhan 4x150 MW thermal power plant insulation application

Çayırhan Thermal Power Plant — 4×150 MW CFPP

Ankara2000–2002Client: Güriş Holding

Scope

  • Plant-wide total of 110,000 m² of insulation application
Orhaneli 210 MW thermal power plant FGD insulation

Orhaneli Thermal Power Plant — 210 MW

Orhaneli · Bursa, Türkiye1999–2001Client: NOEL – KRC – Siemens

Scope

  • Flue Gas Desulphurisation Plant (FGD Area) — Complete Insulation Scope
Paper & Wood Panel Industry

EPC Turnkey Plant Construction Reference

Camsan MDF III plant EPC construction 1 Camsan MDF III plant EPC construction 2 Camsan MDF III plant EPC construction 3

Camsan MDF III — Turnkey (EPC) Plant Construction

Ordu2019–2021Client: Camsan A.Ş.Process Technology: Dieffenbacher

Scope — Fabrication, Civil Works, Erection, Testing and Commissioning

  • 6,500 t of equipment erection · 3,500 t of equipment fabrication
  • 30,000 m² of enclosed-area civil works
  • Testing, commissioning and start-up
615,592 Man-Hours
Mining & Metallurgy

Selected Recent References in Mining and Metallurgy

Eti Bakır Samsun operations insulation and maintenance

Eti Bakır A.Ş. — Samsun Operations

Tekkeköy · Samsun, Türkiye2007 – OngoingClient: Eti Bakır A.Ş.

Scope — Long-Term Framework

  • Plant-wide insulation and scaffolding works
  • Maintenance, repair and all planned shutdowns

More than eighteen years of uninterrupted cooperation: the clearest evidence of trust in long-term maintenance and shutdown contracts.

Eti Bakır Mazıdağı operations insulation 1 Eti Bakır Mazıdağı operations insulation 2 Eti Bakır Mazıdağı operations insulation 3 Eti Bakır Mazıdağı operations insulation 4

Eti Bakır A.Ş. — Mazıdağı Operations

Mazıdağı, TürkiyeSince 2017Client: Eti Bakır A.Ş.

Scope

  • Plant-wide insulation works
  • Spherical ammonia tanks — complete hot and cryogenic insulation scope
Alkim Çayırhan sodium sulphate plant insulation 1 Alkim Çayırhan sodium sulphate plant insulation 2

Alkim Alkali Kimya A.Ş. — Çayırhan Sodium Sulphate Plants

Ankara2010–2011Client: Alkim Alkali Kimya A.Ş.

Scope

  • Turnkey plant insulation works
  • Cihanbeyli Sodium Sulphate Plant insulation works in the same year and scope
Eti Alüminyum Seydişehir plants insulation 1 Eti Alüminyum Seydişehir plants insulation 2 Eti Alüminyum Seydişehir plants insulation 3

Eti Alüminyum A.Ş. — Seydişehir Plants (3 Turnkey Projects)

Seydişehir · Konya, Türkiye2009–2011Client: Eti Alüminyum A.Ş.

Scope — Insulation, Piping and Scaffolding Works

  • 120 t/h Fluidised Bed Power Plant (2009–2011)
  • Electrostatic Precipitator Project — under ELEX management (2009)
Critical Infrastructure

Selected Recent References in Critical Infrastructure

Istanbul Airport ATC tower mechanical and insulation works 1 Istanbul Airport ATC tower mechanical and insulation works 2 Istanbul Airport ATC tower mechanical and insulation works 3

İGA Istanbul Airport — ATC Control Tower

Istanbul, Türkiye2018–2020Main Contractor: MNG

Scope

  • ATC Control Tower — HVAC, insulation, piping and fire system installation
  • 100 of the 116 FLB units — complete mechanical, HVAC, fire and insulation systems

All mechanical works in the ATC tower of Istanbul Airport, the most prominent airport in the region, were completed by ERATHERM.

Kuwait International Airport modernisation project

Kuwait International Airport — Modernisation Project

Kuwait2018–2020Main Contractor: Cengiz Holding

Scope

  • Fire suppression system installation
  • HVAC and piping works
Cement Plants

Selected References in the Cement Industry

Selected records from our experience across 15 cement plants, all covering insulation, piping and scaffolding works.

İzmir Cement Plant2012Fil-Tek Makine İnşaatInsulation · Piping · Scaffolding
Hereke Cement Plant + 135 MW Mobile Power Plant2002–2003Cengiz HoldingInsulation · Piping · Scaffolding
Söke Cement Plant1995–1996ENKA İnşaat ve Sanayi A.Ş.Insulation · Piping · Scaffolding
Kars Cement Plant1992–1997ÇİMTEK / Işıklar HoldingInsulation · Piping · Scaffolding
Elazığ Cement Plant1992–1997ÇİMTEK / Işıklar HoldingInsulation · Piping · Scaffolding
Ergani Cement Plant1992–1997ÇİMTEK / Işıklar HoldingInsulation · Piping · Scaffolding
Further Industrial References

Further Industrial References

SAMGAZ Natural Gas Facilities2009–2011Samgaz Doğal Gaz Dağıtım A.Ş.Insulation · Piping · Scaffolding
Ankara Carrefour · İzmir Kent Hospital · Ankara Bilkent Hospital · İzmir Delphi Automotive2004Tokar Yapı ve Endüstri Tesisleri A.Ş.Turnkey HVAC · Insulation · Piping · Scaffolding
İzmit Fertilizer Plant (İGSAŞ)1998–1999İGSAŞ İstanbul Gübre Sanayi A.Ş.Insulation · Piping · Scaffolding
Metrocity Shopping Centre — HVAC Works1996–1997Yüksel İnşaat A.Ş.Insulation · Piping · Scaffolding
Frequently Asked Questions

Questions About Our References

Does this page list all of ERATHERM's references?
No. This page is not a complete record of more than twenty years of projects but a selection of recent project references . The full reference file covering our portfolio of more than one million square metres of applied insulation, broken down by sector and scope, is shared on request.
Why are defence, aviation and space references not shown here?
The projects we carry out in the defence, aviation and space sectors are covered by non-disclosure agreements , so their scope and content cannot be published. Our capabilities and the work we do in this field are described at a general level on our Defence, Aviation and Space industry page.
What are the man-hour and zero accident figures based on?
The peak workforce, man-hour and delivery performance figures on this page are based on site records approved by the client and the consortium, HSE reporting and progress payment documentation . Each record is documented in the relevant project file.
Can we request a detailed reference file for our project?
Yes. Describe your project scope briefly and send it to [email protected] , or reach us on WhatsApp. A reference file specific to your sector is prepared; details requiring confidentiality are shared after a mutual NDA is signed.

Request a Sector-Specific Reference File and a Quotation

Send us your project scope and we will reply with unit-level references and an engineering-based proposal.